Office order regarding Mega Housing Project, Super Mega Project and Industrial Park Project.
This is a document published by GMADA. This portal links to it for reference and does not host, mirror, or modify the file — it's served directly from gmada.gov.in.
About this document
An office order (Punjabi-language original) from the Punjab Urban Planning & Development Authority's Mega Project Branch, dated 13.12.2019, signed by Sarbjit Singh, IAS, Special Chief Secretary, Department of Housing & Urban Development, Punjab.
What it says
For Mega Housing Projects, Super Mega Projects, and Industrial Park Projects across Punjab whose completion deadline has already lapsed, promoters need to apply in time for an extension to complete them. This order withdraws the exemption from the No-Dues Certificate (NDC) requirement that had previously been granted to such promoters when applying late for an extension (originally granted vide letter No. PUDA-Mega/2017/408-09, dated 11.05.2017).